Work Continues at Jireh

Home
Family
Ministry
Panama
Prayer
Email us!

 

June 2007

Construction work continues at the Jehovah Jireh Good Shepherd School.  All work is being done by volunteers, using the materials purchased and left by the three teams in May.  Here are the highlights of the progress:

1. 2nd story back wall

The 2nd story back wall has been completed, including bond beams and placement of the major I-beam over the columns.  The area around the foundation has been back filled and the construction fence has been removed allowing the children more space.  Still pending is the stairwell, that will be located in the right corner of the photo.

2. 1st story curved wall

The curved wall has nearly been finished.  This wall marks the entrance to the school offices.  Still pending is the bond beam.  Other major work pending on the first floor includes: floors, stucco/painting, electrical, lights, drop ceiling.  The library, located by office area on the left side of the photo, is also unfinished.

3. Sealant and back fill of retaining walls

Two of the three retaining walls have had sealant applied and have been back filled.  The photo to the right is the side between the new building and the apartment building.  This will eventually have the walkway and stairs that will connect the existing school with the administration and library area.

4. First fruits of the new library

School Director Ariela is pictured with our daughter, Stephanie McNamar.  Stephanie's school chose the Jireh school for their charity project for 2007, raising funds and collecting more than 200 Spanish and English books for the new library.  Now all we need to do is finish the library!

 

 

Please pray with us that funds will be given and additional building teams will come to finish construction of the new Jireh School by February 2008.  Offerings may be sent to:

Jireh Project 7795